Complete FCAR, Exterior Wall Testing and Improvements Design
The firm was then hired to provide full design services for the 3 story, 60,000SF improvements consisting of measured drawings, concept design, complete A/E services and interior color/finish selections. Much of the existing wall systems, doors/frames, mechanical/electrical/plumbing systems and other materials were re-used to reduce overall costs. A new chiller and new fire protection sprinkler systems were designed as a part of code updating. The project is currently under construction and is slated for occupancy in Spring 2012.
Owner Satisfaction: Since 2008, HADP and Ivy Group have continually provided professional services to THA. The firm’s continuing working relationship with the client serves as a statement of client satisfaction.
Project Name & Location: Tampa Housing Authority (THA) Cypress West Headquarters OfficesTampa, FL
Firm’s Responsibility:Complete Office Facility Conditions Assessment, Exterior Wall Testing and Improvements Design
Start Date: Winter 2011
Completion Date:Winter 2012
Estimated Cost:$ 2 Million Remodeling Cost
Reference:Mr. David IloanyaDirector of Real Estate DevelopmentTampa Housing AuthorityPh: 813.253.7731